The purpose of the framework agreement is the supply of electricity to the General state administration, its Autonomous Bodies, entities and common services of Social security and other public entities, as well as state entities that expressly request it (within the prescribed in annex I to the PCAP).
The supply of electricity refers to categories of tolls access 2.0 TD, 3.0 TD, 6.1 TD, 6.2 and 6.3 TRADE AND TRADE.
The Framework Agreement is structured as follows:
The characteristics of quality and security of supply are those set out in the regulations of the electricity sector.
The petitioners recruited agencies its provision of electricity to the batch/s precise, through second tenders in it ´ s contracting companies of the framework agreement the characteristics of supply points (CUPS) for and supply its estimate of electricity consumption for periods schedules. Companies contracting of the framework agreement will present their prices, which may not exceed the thresholds set prices in the framework agreement for each company according to its initial offer.
TARIFF STRUCTURE
The rate structure is envisaged in the Circular 3/2020, of 15 january the CNMC, which entered into force on 1 june 2021:
A TARIFF REGIME | ||
---|---|---|
AM Category | Tolls TD (Circular 3/2020 CNMC) | Groups, supply voltage |
1 | 2.0 TD | Low-voltage (BT < 1kV) |
2 | 3.0 TD | |
3 | 6.1 TD | High-Tension (AT > 1 kV) |
4 | 6.2 TD | |
5 | 6.3 TD |
BATCH 1 - PENINSULA >= 1000000kWh | |
---|---|
Order | Companies |
1 | ENDESA ENERGÍA, S.A.U. |
2 | ACCIONA GREEN ENERGY, S.L.U. |
3 | IBERDROLA CLIENTES, S.A.U. |
BATCH 2 - PENINSULA < 1000000kWh | |
---|---|
Order | Companies |
1 | IBERDROLA CLIENTES, S.A.U. |
2 | ENDESA ENERGÍA, S.A.U. |
BATCH 3 - BALEARIC ISLANDS | |
---|---|
Order | Companies |
1 | ENDESA ENERGÍA, S.A.U. |
2 | IBERDROLA CLIENTES, S.A.U. |
BATCH 4 - CANARY ISLANDS | |
---|---|
Order | Companies |
1 | ENDESA ENERGÍA, S.A.U. |
2 | IBERDROLA CLIENTES, S.A.U. |
BATCH 5 - CEUTA AUTONOMOUS CITY | |
---|---|
Order | Companies |
1 | IBERDROLA CLIENTES, S.A.U. |
2 | EMPRESA DE ALUMBRADO ELÉCTRICO DE CEUTA S.A. |
BATCH 6 - MELILLA AUTONOMOUS CITY | |
---|---|
Order | Companies |
1 | IBERDROLA CLIENTES, S.A.U. |
2 | GASELEC DIVERSIFICACIÓN, S.L. |
3 | ENDESA ENERGÍA. S.A.U. |
The duration of this framework agreement is 2 years, since its inception on 15 august 2002. It has been extended for a period of twelve months, until 14 august 2025. It Is likely to be extended for 12 months.
Subdirección General de Contratación Centralizada de Servicios y Suministros para la Gestión de Inmuebles